At 4:30 a.m. on September 6, the construction work of line transfer and dial-up began at Xikeng Station of Xingquan Railway.

In this construction, the Xikeng Station of the Yingxia Railway will be connected and merged into the Xingquan Railway, and the new station building of Xikeng Station will be opened at the same time, making it the only hub station between the two railways. Operation.

The new construction of Xikeng Station started in May 2018. After three years of construction, the original 2 tracks were transformed into 5 tracks with conditions for shunting and storage, which is sufficient for the opening and operation of the entire Xingquan Railway. Ready to serve the development of passenger and freight transportation of Haoxingquan Railway.