He wrote about this in his Telegram.

“The builders have completed the sliding of the fourth, last, superstructure of the left automobile part of the Crimean bridge.

Finished five and a half hours earlier than planned.

This is the result of the high professionalism and experience of the bridgemen,” Khusnullin said.

According to him, in early February, the span will be completely lowered to its design position, and after that the builders will be able to start laying asphalt, installing lighting and barrier fences.

“In March, we expect to open traffic on both sides of the bridge for cars and buses,” he added.

On January 26, Khusnullin announced that the installation of the third span on the left side of the automobile part was completed on the Crimean bridge.