The Xi'an Ring Expressway is the hub section of the main skeleton of the "meter"-shaped highway in Shaanxi. After its completion and opening to traffic, many expressways in Shaanxi and national and provincial arterial roads have been networked in Xi'an.

  On October 26, because the Xi’an South Third Ring Sewage Project under construction was adjacent to the Xi’an Ring Expressway, it was a construction control area of ​​the expressway, and it was forcibly forced without the approval of the expressway management department and the safety assessment. construction.

After repeated blockades, interviews, and "Notice of Correction Ordering" were issued to no avail, the highway law enforcement department mobilized three sprinklers to water the construction site foundation pit under construction for 5 hours on the highway. This incident happened. , Attracted much attention.

  It is understood that the construction unit of the South Third Ring Sewage Project in Xi'an is Xi'an Urban Investment Construction Co., Ltd., and the construction unit is Xi'an Municipal Road and Bridge Construction Co., Ltd.

When the reporter came to the site of the incident, a person in charge of the construction site told the reporter that the Xi’an South Third Ring Road sewage project was a livelihood project in Xi’an. After the incident, the foundation pit was watered by water and was adjacent to Xi’an Third Ring Road and the Ring Expressway. In addition, the traffic volume in the past was relatively high. They were worried that the water seeping in the foundation pit would affect the safe passage of the third ring road. Once the collapse occurred, the consequences would be disastrous.

For this reason, they actively drained water after the incident.

The reporter saw at the scene that there was little water left in the foundation pit.

Regarding whether the project has the approval and construction procedures, Xi'an Urban Investment Construction Co., Ltd. stated that relevant business departments are still investigating.

  Regarding the foundation pit of the irrigation project, the person in charge of the road administration department of the Xi’an City Ring Branch stated that because the site is adjacent to the Xi’an City Ring Expressway, it belongs to the forest belt of the Xi’an City Ring Expressway and is their construction control area. According to China’s "Highway Safety Protection Articles 27 and 28 of the Regulations stipulate that when pipelines, cables and other facilities are buried in the highway construction control area, the construction unit shall submit an application to the highway management agency and submit to the highway management agency a technical evaluation to ensure the quality and safety of roads and road ancillary facilities report.

In addition, the Xi'an Ring Expressway is considering its expansion, and it is necessary to build piers on both sides of the already built Ring Expressway, and the sewage pipes of the construction sites are located at the location of the piers. There is a conflict.

Since the construction on September 10 this year, because the construction party has not submitted a permit for approval to the road administration department of Xi'an Ring Branch, nor has it conducted a safety assessment.

After repeated blockades, interviews, and "Notice of Correction Ordering" were issued to no avail, the road law enforcement department had to resort to this tactic to protect the road rights of the highway, mobilizing sprinklers, and watering the foundation pits on the highway.

  In response to this matter, the Xi'an Municipal Bureau of Housing and Urban-Rural Development convened a coordination meeting with the relevant units involved to determine the suspension of the Xi'an South Third Ring Sewage Project, which was handed over to the design institutes of the two units for docking to reasonably meet the construction needs of the sewage project and the expansion project of the ring road Avoid the position of the piers after the reconstruction and expansion of the surrounding expressway, and avoid secondary excavation. (Headquarters CCTV reporter Wu Chengxuan Bai Longfei)