China News Service, Beijing, February 3 (Xue Lingqiao) "The pumped storage unit can realize two-way rotation operation, and can store reservoir water when the power demand is low. When the power demand is high, the potential energy released by the water can be used to generate electricity. , to meet the power demand”. Recently, a media team from the online themed interview event "Telling the Story of China's New Party System Well" visited the State Grid Xinyuan Hebei Fengning Pumped Storage Power Station, went deep into multiple points of the power station, and explored the "code" of energy wealth deep in the mountains. Meanwhile, Ma Yufeng, a second-level employee of State Grid Xinyuan Hebei Fengning Pumped Storage Co., Ltd., made the above introduction.

  State Grid Xinyuan Fengning Pumped Storage Power Station is located on the main stream of the Luan River in the northwest of Fengning Manchu Autonomous County, Chengde City, Hebei Province. The power station hub project consists of upper reservoir, lower reservoir, water transmission system, underground factory system and other buildings. The upper reservoir has a total storage capacity of 45.04 million cubic meters, a normal water storage level of 1,505 meters, and a maximum dam height of 120.3 meters. The lower reservoir is divided into two parts: a sand retaining reservoir and a dedicated lower reservoir for energy storage. The total storage capacity of the sand retaining reservoir is 13.73 million cubic meters. The maximum height of the sand retaining dam is 23.5 meters. The total storage capacity of the dedicated lower reservoir for energy storage is 71.56 million cubic meters.

  A total of 12 300,000-kilowatt reversible pumped storage power units are installed in the underground power plant, with a total installed capacity of 3.6 million kilowatts. It is the largest pumped storage power station in the world, and its energy storage capacity also ranks first in the world. The first two units of the power station will be put into operation at the end of 2021, and the 12 units are expected to be fully operational in 2024.

  Interior view of the underground factory building of State Grid Xinyuan Hebei Fengning Pumped Storage Power Station Photo by Xue Lingqiao, China News Service

  According to data from the State Grid Xinyuan Hebei Fengning Pumped Storage Company, after all units of the power station are put into operation, the annual power generation is expected to reach approximately 6.6 billion kilowatt hours, which is equivalent to about 5 and a half days of total social consumption in Hebei Province. The electricity consumption is about 19 days of the total electricity consumption in Beijing. In addition, the power station is expected to generate 8.8 billion kilowatt-hours of water pumping power, and social benefits will be greatly demonstrated. The smooth commissioning and operation of the power station will help achieve the "double carbon" goal and promote energy transformation and green development.

  Green power is the main direction of China’s energy green and low-carbon transformation. During the 2022 Beijing Winter Olympics, the power station generated 23.42 million kilowatt hours of electricity and pumped 36.37 million kilowatt hours of water, providing a reliable guarantee for the realization of 100% green power supply and high-quality clean energy transmission for the 26 venues of the Beijing and Zhangjiakou Winter Olympics. .

  Ma Yufeng told the press group that after the power station is fully put into operation, it will save about 480,800 tons of standard coal and reduce carbon emissions by 1.2 million tons every year, which is equivalent to afforestation of more than 240,000 acres, and the ecological benefits will be further extended.

  "In order to implement the concept of 'lucid waters and lush mountains are invaluable assets', the power station has completed a total investment of approximately 290 million yuan in ecological protection. Comprehensive management measures such as vegetation concrete, vegetation bag slope protection, and vegetation blankets are adopted around the power station for different slopes and rock types. , minimizing the disturbance of the original ecology caused by the project construction, and completing ecological restoration of a total of 1.6795 million square meters, committed to creating a business card of Fengning." Ma Yufeng further elaborated on the ecological practices behind the construction of the power station in the lower reservoir exhibition area.

  Rendering of vegetation and concrete greening on the side slopes of the power station road (Photo provided by State Grid Xinyuan Hebei Fengning Pumped Storage Company)

  In rural revitalization, electricity takes priority. According to reports, the State Grid Xinyuan Fengning Pumped Storage Power Station will be able to pay taxes of about 300 million yuan per year after it is fully put into operation, accounting for a quarter of Fengning County's fiscal revenue. In order to effectively connect the consolidation and expansion of poverty alleviation results with rural revitalization, the power station operation actively implements targeted poverty alleviation policies and provides targeted assistance to surrounding Gangoumen Village, Toudaohe Village, etc., and has donated a total of approximately 1.28 million yuan to them for medical treatment and medical treatment for poor households. Public welfare undertakings such as schooling and road construction in remote mountain villages.

  In addition, since February 2018, the power station has signed an agreement with the People's Government of Sichakou Township, and has attracted a total of about 370 employees in logistics services, with an average monthly income of 3,600 yuan per capita, and can generate an annual income of 15.98 million yuan for employees, as well as daily necessities during the construction period, etc. Demand drives local consumption by more than 30 million yuan every year.

  In order to support the industrial development of Fengning County and promote the approval and construction of pumped storage power station projects, leaders of the Central Committee of China Democratic National Construction Association conducted many investigations and actively contacted relevant departments, playing an important role.

  The online themed interview event "Tell the Story of China's New Party System" was hosted by the People's Political Consultative Conference Network and supported by the China Internet Development Foundation. (over)