(Shanghai War Epidemic Record) Fully defend "Shanghai", Shanghai "Clover" Fangcang cabin hospital runs out of speed

  China News Service, Shanghai, April 10 (Zhang Jian, Zhaiyan) On April 9, after four days of hard work, the first batch of 6,748 beds in two independent areas of Shanghai National Convention and Exhibition Center Fangcai Hospital No. 3 and No. 4 were successfully delivered. .

  Since March, affected by multiple factors, the local epidemic situation in Shanghai has shown a rapid development trend.

In order to win this round of epidemic prevention and control, Shanghai continues to renovate centralized isolation and treatment facilities, among which the National Convention and Exhibition Center (Shanghai) has become the largest makeshift hospital in Shanghai.

  According to reports, the project is located in Qingpu District, Shanghai. China Construction Third Engineering Bureau has undertaken the construction of Halls 3 and 4 of the National Convention and Exhibition Center. The area consists of two independent wards with a total area of ​​about 52,000 square meters and can accommodate 6,748 beds.

The project also includes 16 nurse stations and related supporting rooms. There are cleaning areas for medical staff, restricted areas, supporting transportation channels, etc. on the site, and integrated sewage treatment facilities outside the site. Except for the sewage from the command center (clean area) The original sewage pipe network of the site, the other hospital sewage after pre-disinfection, septic tank, secondary disinfection tank, etc., after meeting the effluent quality standard of infectious disease hospital sewage, is discharged into the original sewage pipe in the site.

Photo courtesy of China Construction Third Engineering Bureau

  "I received the instruction to build a makeshift hospital at 1:00 a.m. on the Qingming Festival. As soon as I heard that it was to support Shanghai, I didn't hesitate to get up and enter the standby state. At 4:30 in the morning, I took the bus with the company's first batch of aid construction. "Let's start the team", as the technical director of the sewage treatment system engineering of the treatment site of China Construction Third Engineering Bureau, Liu Jun quickly assembled technical personnel after receiving the construction assistance task, and together with the entire team, it spanned more than 1,500 kilometers and arrived overnight. Shanghai, quickly put into aid construction.

"On the bus, all my colleagues and I contacted the design unit to quickly study the process plan, repeatedly scrutinized the design drawings, and ensured that the technical guidance for the on-site work was in place and that the water could be supplied on time."

  Sewage treatment in Halls 3 and 4 is an important part of the construction schedule and progress of the Fangcang shelter hospital. In theory, the sewage in the Fangcang shelter may carry viruses and must be properly treated.

The sewage treatment systems of these two pavilions adhere to the concept of "quality-based and precise disposal". Medical care and patients are divided into facilities, toilet and fecal sewage are collected separately, and one disinfection and two disinfections are combined.

The whole set of sewage treatment facilities is integrated on the ground and has the characteristics of pressure resistance, elevation control, and anti-seepage.

Photo courtesy of China Construction Third Engineering Bureau

  The construction team of the China Construction Third Engineering Bureau must complete the engineering task with high standards in this extreme test of the race against the "virus".

The construction period is short and the task is heavy. In order to ensure that the sewage is discharged up to the standard, it is necessary to obtain sufficient time for equipment debugging.

"We do not dare to delay the progress for a moment. Equipment procurement actively communicates with competent departments at all levels and material manufacturers to ensure that sewage treatment equipment arrives in time; on-site construction is interspersed, three shifts are arranged, and the equipment on site is installed in place in time. Everything is done as soon as possible. Delivery."

  As of 13:00 on the 9th, the partitions of the ward areas of Halls 3 and 4 have been completed, and the medical and nursing passages, bathroom areas and living areas have been fully completed.

(Finish)