After 9 days and nights of construction, the Shanghai Fuchang Road Health Center Project (fangcang shelter hospital), which was built by the China Construction Third Engineering Bureau, was recently completed and delivered.

  Inverted the progress of the construction period, dispatched more than 1,400 management personnel and workers, worked in shifts 24 hours a day, invested more than 40 sets of machinery and equipment, completed the design plan in 4 hours, completed the construction drawing design in 20 hours, completed the yard work in 22 hours, and completed the box in 5 days. Room splicing and hoisting, electrical and sanitary ware installation and other tasks.

At the same time, the project site strictly implemented prevention and control measures, and completed nearly 20,000 antigen and nucleic acid tests.

(Reporter Xu Yin’s video source is from China Construction Third Engineering Bureau No. 1 Company)