From February 22, 2022, work on the Saint-Brieuc bay wind farm (Côtes-d'Armor) will be able to resume.
This was affirmed on Monday by Ailes Marines, project leader, during the 11th Monitoring and Consultation Body.
The work schedule which runs until 2023 was also presented, reports France 3 Bretagne.
Wind turbines ready by the end of 2023
He indicates that six stations have so far been drilled and two installed.
Hard ground drilling would also be completed.
“We are a little late, but we will be able to recover it entirely in 2023 with the installation of the piles and in parallel with the installation of the electric cables, the foundations and the wind turbines.
We confirm that the commissioning of the wind farm will take place at the end of 2023
,
” explained Emmanuel Rollin, vice-president of Ailes Marines.
A compensation contract would also have been signed with the fishermen in order to compensate for the financial losses.
10 million euros would have been provisioned by Ailes Marines for this purpose.
Justice
Morbihan: A wind farm declared illegal just before its commissioning
Planet
Seine-Maritime: The Fécamp offshore wind farm should produce electricity in 2023
Planet
Saint Brieuc
energy
Environment
0 comment
0 share
Share on Messenger
Share on Facebook
Share on Twitter
Share on Flipboard
Share on Pinterest
Share on Linkedin
Send by Mail
To safeguard
A fault ?
To print