At 11 o'clock on June 16th, Unit 1 of Wudongde Left Bank Power Station, which was undertaken by China Energy Construction Gezhouba Mechanical and Electrical Company, passed the 72-hour trial operation and was officially put into operation, marking that Wudongde Hydropower Station ushered in all units to be put into operation 14 days ahead of schedule. Historic moment.

The Wudongde Power Station is a major national project for the implementation of the "West-to-East Power Transmission". It is the fourth largest hydropower station in China and the seventh largest in the world.

The power station has installed 12 hydro-generator units with a single unit capacity of 850,000 kilowatts, with a total installed capacity of 10.2 million kilowatts. After the power generation is fully put into operation, the average annual power generation is 38.91 billion kilowatt-hours.

Photo courtesy of Gezhouba Electromechanical Company


Release time: 2021-06-16 20:02:27 【Editor: Wang Yi】