[Explanation] On January 19, Hebei Province held a press conference on the prevention and control of the new crown pneumonia epidemic.

According to Yu Wenxue, Deputy Secretary-General of the Hebei Provincial People's Government, Shijiazhuang Huangzhuang Apartment's centralized isolation site entered the site for construction on the 13th. After 6 days and nights of hard work, on the 19th, 606 sets of isolated rooms and supporting facilities will be delivered.

  [Explanation] On the afternoon of the 19th, the reporter saw in the centralized isolation site of Huangzhuang Apartment that most of the main body of the isolation personnel's room on the west side of the isolation point has been completed, and the installation of indoor facilities and outdoor water supply and drainage pipelines is stepping up construction.

According to Zhang Yusong, deputy commander of China Railway Construction Huangzhuang Apartment Construction Headquarters, the Huangzhuang Apartment centralized isolation site project is divided into two phases. The first phase of the project, the fifth and seventh isolation zones of the 1150 isolation personnel, have been completed. .

  [Concurrent] Zhang Yusong, deputy commander of the Huangzhuang Apartment Construction Headquarters of China Railway Construction Group

  Our China Railway Construction is responsible for the No. 5 and No. 7 plots, (responsible for the construction of the first phase) about 1150 isolation rooms, currently the isolation rooms have been completed (main construction), indoor installation, air conditioning and water heaters have been completed The toilet is gradually being installed. The outdoor project is divided into water supply and drainage, power construction and communication construction. Now the outdoor water supply and drainage of the first phase of the project has been completed 80%, the outdoor power supply and power construction has been completed 90%, and the outdoor optical fiber communication construction has been completed. About 95% completed.

  [Explanation] According to Zhai Dongze, the person in charge of the construction site for the isolation site of Huangzhuang Apartment of Hebei Construction Engineering Group, the 1,030 isolation personnel's rooms they are responsible for construction have also been completed, and 606 isolation personnel's rooms and supporting facilities will be delivered on the evening of January 19. facility.

  [Concurrent] Zhai Dongze, the person in charge of the construction site of the isolation site of Huangzhuang Apartment of Hebei Construction Engineering Group

  Our Hebei Construction Engineering Group is currently undertaking the construction of the first phase of the project. There are currently more than 1030 rooms. All the rooms have been assembled and are in place.

Now the main work is indoor and outdoor, water and electricity, pipelines (installation work), in addition to some indoor decoration and the layout of some living facilities.

We are also striving to achieve water and electricity before 24:00 today to meet this condition.

  [Explanation] It is understood that the Shijiazhuang Huangzhuang Apartment centralized isolation site project is located in the south of Huangzhuang Village at the junction of Zhengding and Gaocheng. The actual area of ​​the project is 658 acres, and the construction scale has increased from 3,000 to 4156.

The project will be used for the centralized isolation of close contacts and sub-close contacts of confirmed cases of new coronary pneumonia.

  Chen Shiyu and Wu Jinming report from Shijiazhuang, Hebei

Editor in charge: [Yu Xiao]