(Fighting against New Crown Pneumonia) Builder Liu Cheng: Fighting on the construction site of Mt.

  Chinanews.com, Guangzhou, May 2 Question: Constructor Liu Cheng: Fighting on the construction site of Mt.

  Author Cai Minjie Zhang Jili

  Shenzhen Youth Representative Liu Cheng is the chief commander of the interior project of Wuhan Raytheon Hospital in China Construction Shenzhen Decoration Co., Ltd., a subsidiary of China Construction Decoration Group. During the New Coronary Pneumonia epidemic, he led more than 1,000 builders to fight for 10 days and 10 nights, and finally completed the construction tasks of 4 epidemic prevention hospitals including Vulcan Mountain, Raytheon Mountain, Optics Valley Technology Square Hospital, and Optics Valley Women and Children Square Cabin Hospital.

  On the occasion of the May 4th Youth Day, the Central Committee of the Communist Youth League and the National Youth Federation jointly awarded the 24th China Youth May Fourth Medal to commend the outstanding typical and exemplary representatives of the youth. Liu Cheng became the winner of the 24th "China Youth May Fourth Medal".

  Liu Cheng is 33 years old and is from Wuhan, Hubei. After graduating from college, he joined the China Construction Group Shenzhen Decoration Co., Ltd.

Photo courtesy of respondents from Liu Cheng's family. Photo courtesy of interviewees

  Liu Cheng received the interior task of Raytheon Mountain Hospital at 9:30 on January 30. Unlike the previous acceptance of the engineering order, the company gave him an "order" this time, asking him to form a team and rushed to the site of Raytheon Mountain. Time to complete the interior decoration.

  The decoration project is the most critical part of the construction project, and each project must be used for decoration after the completion of civil engineering.

  Liu Cheng asked: "How short is the shortest?" The company's reply has only two words: "one week".

  The last stick of the construction of Raytheon Hospital in China Construction and Shenzhuang Relay-Part 1 interior decoration project, it is necessary to complete the nearly 20,000 square meters of indoor and outdoor rubber installation work and the laying of 4,000 square meters of toilets and buffer tiles in Wuhan Raytheon Mountain Hospital within one week Work and installation of 316 toilet equipment.

  Normally, the decoration works of a construction project should be prepared from the early stage of structural construction, and a huge decoration volume like Raytheon Mountain can be completed at least half a year.

  Liu Cheng understands that it is now the most critical moment of the epidemic in Wuhan. At this time, the decoration project of Raytheon Mountain Hospital is no longer the usual production task.

  Liu Cheng led the first batch of management personnel to the site of Raytheon Mountain and completed the preliminary work such as site survey, engineering calculation, and model room production within 3 hours. Over the next few days, the entire team struggled on the construction site.

  At 2 o'clock on February 1st, Liu Cheng suddenly received an emergency notice, asking him to set up a team to rush to assist Vulcan Mountain and demand "renovation of 400 wards within two days." A team of 25 management personnel and 150 construction personnel followed Liu Cheng to the Vulcan Mountain construction site.

  "Everyone is hungry and they eat lunch on the construction site. Some colleagues are afraid of going back to the hotel to sleep for a long time. When they are sleepy, they wrap their military coats and lie on the ground." Liu Cheng said, building a Vulcan Mountain Hospital in 10 days, everyone Everyone knows that it is difficult, but only by participating in the construction on the spot can you know how difficult it is.

  The team led by Liu Cheng undertook the "last stick" before the delivery of Vulcan Hill Hospital. They needed to complete a series of interior decoration work such as partition walls, ceilings, doors, and sanitary ware installation in the 5,000 square meter ward area within three days. If it is placed in normal times, such a large amount of interior construction will take about one year.

  In the early morning of February 2, Liu Cheng's wife gave birth to a baby boy by caesarean section and entered the ward. Liu Cheng said, "Wife is working hard." A few minutes later, Liu Cheng returned to the construction site. Before taking the photo, he took a photo of a family of three and posted it online, because the time when the baby was born was just the time when the decoration of Vulcan Mountain was completed and delivered to the hospital. Netizens called it "Vulcan Mountain Baby" ".

  "I give the child a small name An An, safe An. I hope he will always be safe." Later Liu Cheng named his son Liu Mingcan, remember the inscription, the volcano is Can, he asked his son to remember what happened in Wuhan in the spring of 2020 This special battle.

  "Either don't do it, do it and do the best." Liu Cheng said that next he will focus on the resumption of production of the company's projects and the prevention and control of epidemic situations, and make due due to the restoration of urban economic construction. contribution. (Finish)