National Energy Administration: Further strengthen the safety production work of hydropower stations. On January 25, water leaked from the factory building of the Jiniu Hydropower Station of the National Energy Group Dadu River Company.

There were no casualties. At the time of the incident, Unit 2 had just completed maintenance and was in standby mode. An on-site inspection later found that the entrance door of the water distribution ring pipe of Unit 2 was damaged and the fixing bolts were broken.