As the strike of truck drivers continues for the fourth day, the number of construction sites causing setbacks is increasing.

Many of the construction sites in the metropolitan area that are being built by large construction companies have stopped, and as a result of our exclusive coverage, it was confirmed that the large-scale reconstruction site in Gangnam, Seoul was also stopped due to the supply of cement and ready-mixed concrete cut off.

Let's connect with reporters who are out of the field.



Reporter Yoon-ha Cho, I think it was on the Banpo Bridge side, but the construction site you see behind has stopped.



<Reporter>



This is a reconstruction complex being built by a large construction company with a scale of 3,000 households.



However, starting today (the 10th), the construction site also stopped.



The supply of cement and ready-mixed concrete is cut off.



I walked around this construction site for a day today, listening to stories and reporting the situation, but the situation was a bit difficult to the extent that the term paralysis was correct.



From now on, let's take a look at what I personally interviewed in the field.



On the first day of the strike, there was a partial problem because the ready-mixed concrete did not arrive as much as I ordered it four days ago.



So, the construction stopped on the 22nd floor out of the total 35 floors, and the work to raise the 23rd floor was stopped.



I came to the construction site on the 23rd floor of a new apartment building.



Where I stand now, not on the usual floor, but on this rebar.



If it was the same as the original, the floor process should be finished and cement should be laid, but now the process has been pushed and only the rebars remain. This is the place to do it.



However, since the process continues to be delayed, the process has not been completed on the 4th day.



[Field official: There is no worker.

The fact that there is no one is literally because everything has stopped...

.]



Even the stairs to the apartment remain only the skeleton.



The situation is the same in the other Dongdo next door.



[Site staff: Originally, reinforcing bars were supposed to go in, but even if we lay rebars now, we can't pour, so we just stopped the work.] The



same is true on the ground.



I was preparing to plant a steel frame and apply cement in the underground parking lot, but I can't move on to the next process in the same way.



In addition to this construction company, other large construction companies also confirmed that all construction sites in the metropolitan area have stopped.



In just four days after the strike, large construction companies have stopped construction one after another.



(Video coverage: Jeon Gyeong-bae, video editing: Jeon Min-gyu, VJ: Park Hyeon-woo)