China News Service, Taiyuan, November 23 (Gao Yuqing) By the end of 2021, Shanxi will supply 53 million tons of electric coal to 14 provinces, autonomous regions and municipalities. In order to alleviate the urgent need for burning "coal", Shanxi has put on an "accelerated gear."

The reporter learned from the Shanxi Provincial Energy Bureau on the 23rd that up to now, the province has supplied 21.87 million tons of electric coal to 14 provinces, autonomous regions and municipalities.

  Shanxi is a major coal province in China and is known as the "ballast stone" for national energy security.

According to statistics from the Shanxi Provincial Bureau of Statistics, in the first 10 months of this year, Shanxi’s coal output was 980 million tons, an increase of 11.1%.

  At the end of September, Shanxi signed contracts with 14 provinces, autonomous regions, and municipalities including Hebei, Shandong, Guangxi, and Tianjin to guarantee the supply of coal in the fourth quarter to ensure energy supply.

  Among them, Shanxi’s largest coal-producing company Jinneng Holding Group is responsible for the fourth-quarter guarantee of supply in 6 provinces, autonomous regions and municipalities including Guangxi, Jiangsu, Jilin, Anhui, Shanghai, and Zhejiang; Shanxi Coking Coal Group, Huayang New Materials Group, and Lu’an Chemical Group respectively Undertake the task of guaranteeing supply in Henan, Hainan and Shandong; the remaining tasks of guaranteeing supply are undertaken by coal enterprises in Shanxi Province.

  The relevant person in charge of the Shanxi Provincial Energy Bureau said that in order to promote the completion of the national task of safeguarding 53 million tons (7 million tons of mobile) electric coal in 14 provinces, autonomous regions and municipalities, coal enterprises in the province have strengthened production scheduling under the premise of ensuring safety. Fully release coal production capacity and strive to increase coal production.

  Since October, Shanxi's average daily coal output has remained above 3.3 million tons, and the monthly coal output in the third quarter has exceeded 100 million tons.

At present, the production coal mines in the province are producing at full capacity, and 46 million tons of contracts have been signed.

  In addition, Shanxi has made every effort to ensure the use of coal for power generation companies in the province, and promoted the signing of medium and long-term coal contracts for power and heating companies.

Up to now, Shanxi Province’s power generation and heating companies have signed up to 43.14 million tons of medium- and long-term contracts, and a total of 115.57 million tons have been signed throughout the year, and the coverage rate has reached 100%.

At the same time, we will make every effort to stabilize the power delivery to ensure the safety of electricity in the capital area.

  According to estimates by relevant departments, Shanxi's coal production is expected to exceed 1.2 billion tons this year.

The relevant person in charge of the Shanxi Provincial Energy Bureau stated that the next step will be to promote the fulfillment of the guarantee contract to ensure the safe and stable supply of electricity and coal in 14 provinces, regions and municipalities.

At the same time, strengthen the monitoring and analysis of energy operation, take emergency precautions against extreme weather in time, and ensure the safe and stable operation of energy supply.