Xinhua News Agency, Lhasa, July 16 (Zhang Wei, Wu Yunhui, and Liu Yangyang) A reporter learned from Huadian Jinsha River Upstream Hydropower Development Co., Ltd. (referred to as "Huadian Jinshang Company") on the 16th that Tibet's first installed capacity of 1.2 million kilowatts was the first million kilowatts in Tibet. -Level power plant-Suwalong Hydropower Station project, the first generator set, the generator floor of Unit 4, successfully met on the 15th, and officially entered the stage of electromechanical installation.

  According to Yang Tongshun, deputy director of Huadian Jinshang Office, Suwalong Hydropower Station is located in the upper reaches of the Jinsha River at the junction of Mangkang County, Changdu, Tibet, and Batang County, Ganzi Tibetan Autonomous Prefecture, Sichuan. The total investment is 17.89 billion yuan, and the annual power generation is 54.32. Gigawatt-hours is the first project to be approved for construction on the upper reaches of the Jinsha River, and it is also a pilot project for China's "West-to-East Electricity Transmission" succession base and the National Water, Wind, Solar, and Renewable Energy Demonstration Base.

  "Since the start of construction was approved in November 2015, the development and construction of the Suwalong Hydropower Station project has proceeded smoothly." Yang Tongshun said that the first generator set's generator layer was completed on schedule, marking the goal of commissioning power generation by 2021. A solid step.

  Yang Tongshun told the China News Agency that the next step, Huadian Jinshang Suwalong Branch will arrange the construction period reasonably and promote the three key projects of dam, factory building and diversion tunnel with high quality. "At present, 36% of the dam is filled, 82.5% of the concrete pouring of the plant is completed, production preparation personnel are in place, and work such as on-site regulations and regulations is progressing simultaneously." (End)