Traffic on the Chaban-Delmas bridge will be very disrupted from next Monday, May 2, until Friday, May 27.

During this period, cleaning work will be carried out on the structure.

On Monday, the bus lanes will be closed, then from May 3 to 9, the traffic lanes will be cut intermittently: that in the north-south direction for three days, then that in the south-north direction for a maximum of three days as well.

Then from May 10 to 27, the pedestrian bridges will in turn be closed intermittently (pedestrians and cyclists will be basulated on the pedestrian bridge that remains open).

More information on the site of the metropolis of Bordeaux. 