The corresponding statement was published on the company's website.

“Today the specialists of the Far Eastern Distribution Grid Company have put under voltage the restored 110 kV line, which provides power supply to the Pervomaisky district of Vladivostok.

Thus, the electricity supply has been restored to all districts of the capital of the Primorsky Territory, "RusHydro noted. 

It is noted that repair work on the damaged power line was carried out around the clock, power engineers dismantled the fallen ones and installed three new supports, replaced the wire, traverses and insulators. 

"At present, power engineers continue emergency recovery work in distribution networks in the settlements of the Primorsky Territory," the company added.

Earlier, a representative of the Vladivostok Enterprise of Electric and Heat Networks MUP spoke about the situation with heat supply in Vladivostok.

On November 23, the Governor of Primorsky Krai, Oleg Kozhemyako, assessed the preliminary damage from bad weather in the region.