Artist's impression of the CHU station of the future Toulouse cable car. - Tisseo SMTC - Smat - Poma

  • The stoppage of the site due to confinement will cause a delay in the opening of the Toulousain urban cable car.
  • And it is not excluded that the health crisis also has repercussions on the timetable for the third metro line.

"The site is stopped and Téléo will probably not open before the end of the year". Unsurprisingly, Francis Grass, the president of Tisséo Engineering, confirms that the famous Toulouse urban cable car, the opening of which was announced for the end of 2020, will not pass over confinement.

When everything stopped, the companies had just completed the foundations of the three stations and those of the giant pylons which will support the cables so that the cabins can connect the Oncopole to the Paul-Sabatier University via the CHU de Rangueil . The “pillars” of the cable car will therefore not be erected as planned at the start of the summer

"We do not yet know to what extent companies will be able to gradually resume work," continues the technician. And it is more of a project that involves sub-contractors, which makes the organization of the takeover even more complex ”. Not to mention that the specialized manufacturer Poma, which won the cable car tender, is partly supplied ... in Italy.

Toulouse residents will therefore have to wait longer than expected to travel over traffic jams and Pech-David hillsides. "But this is not very serious given the major health issues of the moment," relativizes Francis Grass.

What about the metro?

Regarding the third metro line, the opening of which is officially scheduled for 2025, we say that the confinement will not have an impact since the structural work has not started. "The teams are continuing the study phases in teleworking", underlines the president of Tisséo Engineering. But he also adds that "the operations related to the purchase of land had to be stopped". In addition, at the request of the applying manufacturers, the opening of the “envelopes” on the rolling stock which will equip the line was postponed by two months, from April 14 to mid-June. “There is no mystery. We are losing several months on certain aspects of the project, concedes Francis Grass. Can we catch them? We can't say it today, ”he concludes cautiously.

Toulouse

VIDEO. Toulouse: Téléo, the future pink city cable car, is anchored to the ground to gain height

Toulouse

Coronavirus in Toulouse: Public transport users, here's how you can get reimbursed

  • Construction site
  • Containment
  • Covid 19
  • Coronavirus
  • Tisséo
  • Public transport
  • Toulouse