China News Service, Xiong'an, April 1st, title: The third anniversary of the establishment of Xiong'an New District: high-quality project promotion

China News Agency reporter Cui Tao

On April 1st, Xiong'an New Area, which bears the “millennium plan”, commemorates the third birthday of Shenzhen Special Economic Zone and Shanghai Pudong New Area. Xiong'an New District's high-quality planning system has basically formed and has entered a large-scale development and construction stage. At present, 78 projects in Xiong'an New District have resumed work, 1049 companies have resumed production, and 58,852 people have returned to work (projects).

Xiong'an Campus of Beihai Kindergarten: Taking back the lost time

"The time delayed by the epidemic should be taken back and the project should be completed as scheduled." Yin Jian, project manager of Xiong'an Park, Beihai Kindergarten, China Construction Eighth Bureau, is directing multiple construction teams to carry out the orderly construction.

The Beihai Kindergarten Xiong'an Park project, one of the turnkey projects for the construction of the "three schools and one hospital" in Xiong'an New District in Beijing, has taken 120 days since the start of construction on September 20, 2019. Substructure construction phase.

Affected by the epidemic, the Beihai Kindergarten Xiong'an Park project officially resumed work on February 18. However, due to the lack of construction personnel and a slow progress, Yin Jian and more than 10 managers from the project department joined the "fight", greatly speeding up the construction progress and surviving the difficult period of lack of workers.

Song Fei, the project's safety director, said that the project management is very strict. The living areas and enclosures are all set in accordance with the standardized model set by the company. They also have strict requirements in terms of reducing noise and suppressing dust. follow the rules.

Yin Jian said that the design concept of the project continues the historical heritage of "red walls, green trees and white towers", and fully considers the needs of children's outdoor activities, and reasonably integrates into patriotic education areas, physical development areas and scientific exploration areas. During the construction process, the project is constructed in accordance with the latest three-star standard "Green Building Evaluation Standards", which has strict specifications on environmental protection, energy saving, and heat preservation standards for building materials.

Rongdong Underground Comprehensive Pipe Gallery: Smart Unmanned Car

"The underground comprehensive pipe gallery we are building is quite special. The bottom is a four-cabin integrated pipe gallery, and the upper one is a two-cabin logistics gallery. The average depth of the foundation pit is 14 meters." In Rongdong, Xiong'an New District, CCCC First Public Bureau Group Co., Ltd. Yin Pengfei, deputy chief engineer of the project at the construction site of the BC Community RDSG-3 tender section (hereinafter referred to as Xiong'an Rongdong 3), said that the lower-level pipeline corridor is used to integrate power, gas, communication, water supply and drainage pipelines, and the upper-level logistics corridor The road can run intelligent unmanned vehicles for logistics distribution in the park, and can directly send items to terminals such as office buildings and residential buildings.

The Xiong'an Rongdong No. 3 bid is located in the eastern part of Rongdong area. It mainly includes the construction of municipal roads, bridges, pipe corridors and drainage pipe networks. The main engineering quantities are six municipal roads of "four horizontal and two vertical" with a total length of 7.58 kilometers and a comprehensive pipe corridor. 2.91 kilometers, 2.25 kilometers underground logistics corridor.

"The original 15-month construction period was due to the sudden epidemic situation and the need to cooperate with the overall project progress in the area. The actual construction period was only about 12 months. In order to ensure that the project can be delivered on time and quality, within 20 days, we will The number of workers has increased from 200 to 800, and will continue to increase to 1500 in the future. "Said Zhang Guocheng, the project executive manager, and also increased the configuration of machinery. Among them, tower cranes increased from 5 to 9 and crawler cranes. Increase the number of machines by 7 to fully guarantee the progress of the project.

Zhang Guocheng pointed at the display sand table and said that the comprehensive pipe gallery is not just a city's "lifeline", it is like the city's "five internal organs and six stilts". After the completion, the gas, power, communication, and sewage pipes will be collected into this pipe gallery. The "big pocket" guarantees the safe and efficient operation of power supply, drainage heating, and fiber optic cables. In the future, the underground space of this park will extend in all directions. At the same time, the park will also be covered with greenery and ecologically livable. "There will be an artificial lake here, and municipal roads will pass through the tunnel at the bottom of the lake."

Xiong'an Business Service Center: Striving for "Luban Award"

Xiong'an Business Service Center is the first batch of housing construction projects in Xiong'an New District. It is the first iconic housing construction project invested by China Xiong'an Group Co., Ltd. after Xiong'an Citizen Service Center. The comprehensive start of construction has a huge leading role and will become one of the most influential business card projects in Xiong'an New District.

Entering the project construction site of Xiong'an Business Service Center, more than 600 workers were tying steel cages in the foundation pit of the project site, the first bidding section of the project.

"The total construction area of ​​the Convention and Exhibition Center project is 83,000 square meters, of which 41,000 square meters are underground and 42,000 square meters above ground. The new zone will position it as the Xiong'an Science and Technology Achievement Exhibition and Trading Center, mainly to protect the important conference and exhibition functions of the new zone in the next 5 to 10 years. "Said Fu Lin, the project construction director of the Xiong'an Business Service Center of the China Construction Third Bureau.

According to Fu Lin, the main contents of the project construction include hotels, business office buildings, expert apartments, serviced apartments, commerce, kindergartens, service facilities, conferences and exhibitions, Xiong'an International Scientific and Technological Achievements Exhibition and Trading Center, and underground parking lots. After the project is completed, it will effectively complement the various business service supporting functions that are urgently needed in Xiong'an New District in the near future.

Fu Lin said, "We will strive for the Luban Award for Chinese Construction Engineering (National Quality Project)." (End)