Abu Dhabi Public Services Company (Masada) has handed over two projects for the internal roads and infrastructure in Al Rahba City, in cooperation with the Abu Dhabi Municipality, at a cost of AED 453 million on an area of ​​approximately 3 million square meters.

The two projects included land leveling, as well as relocation and relocation of some infrastructure services.

Masada explained that the first project included the implementation of internal road works with other service facilities such as sewage, rainwater drainage, drinking water and lighting of internal roads, serving 519 housing units and a road network of 11 kilometers.

Ansada extended 108 km of power cables, built 29 power stations, installed water lines with different diameters with 28.7 km long extensions, and set up a 22.2 km sewerage network to cover vouchers, add future statements, and transfer service lines that are in conflict with Roads, as well as the implementation of a 17 km long rainwater drainage network.

The second project included the construction of internal roads, parking lots and infrastructure to serve 671 construction vouchers, including 17 kilometers of internal roads and 16 km of rainwater drainage.

It also included the construction of a 39-kilometer drainage network, including a 10-kilometer main drainage and lift station, the construction of a 35 km long drinking water network, the extension of 145 km of power cables and the establishment of 36 substations.