“On July 10, the state-owned specialized enterprise (GSP)“ Chernobyl NPP ”will put into operation a new arch over the destroyed fourth reactor, President Vladimir Zelensky will take part in the events,” said Zelensky’s press secretary on her Facebook page Julia Mendel.

On July 9, it became known that the Ukrainian state-owned specialized enterprise Chernobyl Nuclear Power Plant on July 10 will put into operation a new safe confinement (NSC) of the company NOVARKA, built over the destroyed fourth power unit.

In April, Prime Minister of Ukraine Vladimir Groysman visited the new Shelter Confinement, which successfully completed a 72-hour trial operation. It was reported that the project was completed at 99%.

Earlier it was reported that the European Union will allocate € 3 million to ensure nuclear safety in Ukraine.