Reached the "equator": the builders laid half the rails on the Crimean bridge
2019-03-14T19:43:22.403Z
The builders laid half of the rail track on the railway part of the Crimean Bridge - 19 out of 38 km. Rails and sleepers are assembled in 25-meter links on the Taman Peninsula and are transported in this form. In August 2019, the first technological train should pass over the bridge. Also began the installation of architectural lighting elements on the railway arch. It will be made in the colors of the Russian flag, the testing system is scheduled for July. Completely complete all work planned for December. The railway through the Kerch Strait will be continuous and will be able to withstand a nine-point earthquake.
Source: russiart