Builders commented on the appearance of trains on the Crimean bridge

8/9/2019, 8:16:03 PM

The builders of the Crimean bridge, commenting on the appearance in the network of personnel with trains on the bridge, said that technological trains have been going through the construction since last year, RIA Novosti writes.


As noted, the rails laid between the two banks are necessary for the workers of the builders.

“Cars moving along with rubble for ballasting, track machines for straightening and straightening tracks, welding rails in a whip on different sections of the bridge and approaching it from the side of Kerch,” the Crimean Bridge Information Center said in a statement.

On July 18, the laying of rails was completed on the Crimean bridge. Two brigades working from different ends of the structure closed the railway line.

It is expected that traffic on the railway part of the bridge to the Crimea will open on December 9-10.