The dismantling of the tower crane at the site of the Gwangju apartment collapse, which was scheduled to be completed by the 22nd, is being delayed.



According to the site judgment during the dismantling of the crane, the top form of the building was removed first, but during the dismantling of the crane, the dismantling work was halted due to abnormal signs on the exterior wall in the process.



However, as the crane stabilization work was done first, the authorities believe that there will be no major risks in the future.



Search operations for the five missing persons will resume today.