China News Service, Beijing, December 16 (Reporter Chen Hang) The reporter learned from the operation team of the Shougang Ski Jump Stadium that the functional acceptance of all temporary facilities in the closed loop of the Shougang Ski Jump has been completed. This acceptance involves 13 business areas of the stadium team , The scope covers board houses, tents, temporary stands, cable routing, temporary routing, hard isolation, barrier-free and other related facilities. These temporary facilities will serve customer groups such as athletes, media, and large families during the game.

  It is reported that this acceptance is based on the requirements submitted for approval and confirmation in the early stage of each business field. Each user conducts a comprehensive inspection of the internal function layout, lighting, heating, ventilation, water supply and drainage and related facilities of the relevant buildings. After investigation, All facilities meet the requirements of the event. This acceptance also means that all the infrastructure required for the Shougang Ski Jumping competition has been in place, and the venues have the conditions for the event to be held.

The functional acceptance of all temporary facilities in the closed loop of Shougang Ski Jump has been completed.

Photo courtesy of Shougang Ski Jump Stadium Operation Team

Temporary facilities are wide in scope and large in total

  Shougang Ski Jump is the only snow venue in Beijing, with a large total of temporary facilities and a wide range of types.

In addition to obvious temporary houses such as waxing room, athlete rest room, athlete medical station, venue media center, broadcasting complex, etc., temporary camera platforms, stands, large screen brackets and other supporting structures, temporary cable flyovers, pipeline channel brackets, etc. Other wiring facilities are also within the scope of temporary facilities.

  The Shougang Ski Jump will host the Beijing Winter Olympics Snowboard Jump and Freestyle Ski Jump. This is the first time that the Winter Olympics Jump will be held in a city. The requirements for facilities are more obvious than those in mountain venues and indoor venues. Differences, such as the setting of the snow storage area on the venue, have no precedent for the previous Winter Olympics.

The facility team completed the design and construction of the snow storage area based on the snow storage requirements of the snow storage area, combined with the site conditions, and after multiple mechanical analysis verifications.

Keep a safe distance within the comfort zone

  In the context of the epidemic, epidemic prevention standards have been integrated into the entire construction of temporary facilities for the Shougang ski jumping platform, such as the installation of isolation rooms.

At the same time, according to the safety protection distance requirements of the customer group, the facility team reasonably uses the soft and hard isolation to keep the customer groups such as athletes, media, and large families at a safe distance within a comfortable range.

  The operation team of the Shougang Ski Jump Stadium stated that under the background of the epidemic, it is difficult for foreign experts to arrive at the venue, and the actual construction of the venue is difficult to visually display, and various wiring conditions can only be communicated with foreign parties through related methods such as videos and pictures. , The facility team overcomes difficulties by accelerating the frequency of video conferences and organizing remote inspections to ensure that various facilities in the venues meet the requirements for use of the Winter Olympic Games.

(Finish)