6 people injured in the explosion of Guanghan Jinyan Fireworks Factory were preliminarily recognized as general accidents

  On July 10, the Deyang City Emergency Management Bureau notified the "7·8" general fire and explosion production safety accident of Guanghan Jinyan Fireworks Factory. The specific report is as follows.

  At about 21:10 on July 8, 2020, the lead workshop of the Nanfeng production area of ​​Guanghan Jinyan Firework Co., Ltd. was burned. After receiving the report, relevant departments such as emergency, public security, and firefighting rushed to the scene for rescue as soon as possible. Through on-site investigation, it was understood that the plant and products were not of high value, and the possibility of explosion was extremely high. To ensure the safety of personnel, the person in charge of the site command ordered the immediate cessation of fire fighting, and organized party and government cadres to evacuate all surrounding people.

  At 10:25, an explosion occurred in the lead workshop. After continuous efforts by the emergency, firefighting, and public security departments, the fire at the accident site was completely extinguished at 4:20 in the morning of July 9; at 5:05, the site disposal was completed. To prevent re-ignition, there are still 10 people left behind to monitor the scene. Six people were injured in the accident, including two seriously injured and four slightly injured. One person was discharged as of 10 o'clock on the 10th.

  On July 9, the Deyang City People's Government organized the establishment of an accident investigation team to start an accident investigation. After a preliminary investigation, the cause of the accident was that the nitrocellulose in the chemical raw material warehouse released heat under the action of high temperature (weather) and other factors. The accumulated heat spontaneously ignited, causing the charcoal in the adjacent warehouse to catch fire, and then ignited the ignition line stored in the adjacent building. The first deflagration immediately ignited the second deflagration of the ignition line stored in the building 90 meters away. The total economic loss was about 500,000 yuan. The preliminary judgment was a general accident. Accidents will be subject to formal accident investigation reports.

  For the raw materials such as the igniter line and other stocks in the Nanfeng production area, the provincial emergency expert team will formulate a disposal plan. On the afternoon of July 9th, 18 professionals and 3 special vehicles for transportation will be organized for transshipment in the early morning of July 10. When finished, completely eliminate hidden dangers.

  Song Haoxin