Chinanews.com, Dalian, January 15th (Reporter Yang Yi) On the evening of January 14th, it was the traditional "Little New Year's Eve" in northern my country. The only seaside football field surrounded by the sea on three sides in China-Dalian Suoyu Bay Football Stadium project was launched. The light system is in full bloom, creating a festive and peaceful festive atmosphere, and sending Chinese New Year blessings to the local people.

  The Dalian Barracuda Bay professional football field project is invested by the Dalian Municipal Government, and the EPC general contractor is the Northeast Branch of China Construction Eighth Engineering Bureau.

The project started construction in October 2020. The total area of ​​the project is about 265,000 square meters, and the total construction area is about 136,000 square meters. It is positioned as a 63,000-seat super football field and is the first professional football field in Dalian.

The picture shows the brilliant blooming of the floodlight system of the Dalian Barracuda Bay Football Stadium Project.

Photo courtesy of China Construction Eighth Bureau Northeast Company

  The architectural design of this project is inspired by "waves and conch": the building has a beautiful and dynamic appearance, and its skin looks like the sparkling sea surface, reflecting the coastal cultural characteristics of the romantic city of Dalian; The city spirit of moving forward and striving upward.

  Su Xinhe, Secretary of the Party Branch of the Dalian Barracuda Bay Football Stadium Project, introduced that the facade of the project is composed of an ETFE cable-membrane structure and a surrounding cable-membrane floodlighting system.

Among them, nearly 40,000 square meters of ETFE membranes are used for the facade, including 9 kinds of blue membrane materials and 7,823 pieces of membranes. It is currently the project with the largest membrane structure coverage of professional football fields in the world and the most single-layer ETFE membrane structure.

The picture shows the brilliant blooming of the floodlight system of the Dalian Barracuda Bay Football Stadium Project.

Photo courtesy of China Construction Eighth Bureau Northeast Company

  The floodlight system of the project includes more than 17,000 sets of LED linear lights on the wall, 784 sets of 280W LED floodlights and 420 sets of 420W LED floodlights on the ceiling. The overall floodlight is mainly dynamic light, supplemented by static floodlight. There are three different modes: festival, weekday, and night. The main color is "blue sea and white clouds".

  Su Xinhe said that the installation of the overall diaphragm will start on October 10, 2022, and the facade will be closed on November 20; The overall debugging was lit, and it was lit for the first time on December 31; after intensive debugging, the overall animation effect was even more shocking, and it was finally presented perfectly on New Year's Eve.

(Finish)