China News Service, Taiyuan, July 15 (Reporter Yang Jieying) Many people were punished due to perfunctory rectification of environmental protection issues and serious violations of laws and regulations.

On the 13th, Shanxi notified the second round of the investigation and accountability of the transfer of the central ecological and environmental protection inspectors.

The notice mentioned that the Xiigou Coal Mine of Shanxi Coking Coal Group had perfunctory rectification and serious violations of laws and regulations.

  According to the report, the Xiigou Coal Mine, a subsidiary of Shanxi Coking Coal Group, has not implemented the rectification of the first round of central ecological and environmental protection inspectors for failing to implement environmental protection requirements and unauthorized commissioning. EIA change procedures, failure to go through the procedures for entering the river sewage outlet in accordance with the law, and illegal water intake.

The Lvliang City Administrative Examination and Approval Service Bureau overstepped its authority to approve the environmental impact report of the Xiigou Coal Mine and Coal Preparation Plant's Ditch Filling and Land Reclamation Project.

Shanxi SASAC, as the responsible unit for rectification and cancellation of accounts, has not strictly controlled the rectification and cancellation of accounts, and canceled accounts in violation of regulations.

  According to the management authority of cadres, Wu Huatai, the then secretary of the Party Committee and chairman of Shanxi Coking Coal Group, was given a serious warning within the party; Jin Zhixin, the general manager of Shanxi Coking Coal Group at the time, was given a warning within the party; He served as deputy director of SASAC of Shanxi Province to criticize education; to talk to Liu Wei, then director of the Planning and Development Department of SASAC of Shanxi Province; to give advice to Che Yongli, the second-level investigator of the Assessment and Distribution Department of SASAC of Shanxi Province; Liu Zhequn, Secretary of the Party Committee and Director of the Approval Service Administration, Yang Xiping, then Deputy Director of the Lvliang Administrative Examination and Approval Service Administration, Cui Xudong, Secretary of the Party Committee of Xishan Jinxing Company, and Wang Yubao, Secretary of the Party Committee and Chairman of Xishan Coal and Electricity Power, received warnings from the party; Song Jianjun, General Manager and Chairman of Jinxing Company, Wu Guotao, Deputy General Manager of Xishan Jinxing Company at that time, Liu Xiaojun, Secretary of the General Party Branch and Director of Xiegou Mine Coal Preparation Plant of Xishan Jinxing Company, Xishan Jinxing Company Xiigou Coal Preparation Plant Chen Yunfeng, chief engineer, was punished for major demerits; Guo Fuzhong, then general manager of Xishan Coal and Electricity Company, Hu Zhiwei, chief engineer of Xiegou Mine of Xishan Jinxing Company, Bian Junqi, then director of Xiegou Mine of Xishan Jinxing Company, and general manager of Xishan Jinxing Company Manager Li Zhihai, then director of Xishan Coal and Electricity Environmental Protection Division Zhao Xinmin, and chief engineer of Xishan Coal and Electricity He Zhihong were given administrative demerit punishments. Tian Yunfu, deputy director of the Environmental Protection Department of Xishan Coal and Electricity, and Huo Xueping, director of the Environmental Protection and Health Management Department of Shanxi Coking Coal Group, were given government warnings.

  In April 2021, the Central No. 1 Ecological Environmental Protection Inspectorate inspected the Xiigou Coal Mine of Shanxi Xishan Jinxing Energy Co., Ltd., a subsidiary of Shanxi Coking Coal Group, and found that the relevant departments and companies pointed out problems to the Central Ecological Environmental Protection Inspector perfunctorily and made surface rectification. , The problem of ecological damage in the development of coal resources is prominent.

  The inspection team reported that Shanxi Coking Coal Group is the country's largest coking coal production and processing enterprise and the country's largest coking coal market supplier.

The location of Xiigou Coal Mine is a national key ecological function area with restricted development, a core area for soil erosion control in the middle reaches of the Yellow River and a key area for soil erosion control in the Loess Plateau.

  The inspector found that, in order to illegally build a gangue dump, the Xiigou Coal Mine in the natural ravine area of ​​the Loess Plateau has cut down hills and slopes, dumping tens of millions of tons of gangue in the dump, and then used the loess taken from the mountains and slopes. covered on top.

  Due to outstanding problems such as inconsistency of approved construction and construction before approval, Xiigou Coal Mine has not been able to meet the environmental protection acceptance conditions for a long time after its completion, and it has also failed to meet the rectification task target requirements of "complete environmental protection acceptance within a time limit".

Shanxi Coking Coal Group, as the responsible unit, perfunctory on the rectification task, knowing that the environmental protection acceptance has not been completed, it reported that the rectification task has been completed, and submitted a request for the rectification and cancellation of the number to the Shanxi Provincial State-owned Assets Supervision and Administration Commission.