According to the municipality, the reason behind the price level is due to a lack of competition in the construction industry in the Ore Fields together with the current world situation with rising material prices and uncertain deliveries.

The bids were higher than planned.

The procurement is interrupted, but the project of casting the base plate on the bottom floor continues during the summer and autumn.

Contractor for that work is already contracted.

Will replace what disappears in the ore mountain

The multi-activity house is intended to contain premises for activities in leisure and culture, such as adventure swimming, bowling, sports hall, cinema, black box and library.

A large part of the house is a replacement for what is being demolished in Malmberget.

The delay of the multi-activity building thus also creates problems for the operations that will move from the sports hall, which according to the forecast will be closed down by the turn of the year.