In order to ensure that the Chongqing-Qianjiang railway of the Chongqing-Xiangjiang high-speed railway is completed and opened to traffic as scheduled, during the "May 1st" holiday, the builders of the high-speed railway gave up rest, seized the construction progress, and spent their festivals on their posts.

  The reporter saw at the construction site of the Wulong Guojiashan Tunnel of the Chongqing-Qianjiang High-speed Railway from Chongqing to Qianjiang. The machines in the tunnel were roaring. More than 1,200 construction workers were dispatched by the commander to carry out intensive work in various areas of the tunnel. The site was busy. scene.

  The Chongqing-Qianjiang Railway Guojiashan Tunnel of the Chongqing-Xiang High-speed Railway is a Class I high-risk tunnel with a total length of 4,597 meters.

On October 1, 2020, the tunnel construction started, and the main tunnel has been excavated for 1,700 meters, and the project is progressing smoothly.

  The Chongqing-Qianjiang Railway is an important part of the Xiamen-Chongqing Corridor in the national "eight vertical and eight horizontal" high-speed rail network. The main line is about 269.5 kilometers long and has a design speed of 350 kilometers per hour.

(Wang Jinchuan, Wang Yi, Xiao Jiangchuan)