“In connection with the satisfaction of the petitions of the persons participating in the case, in connection with the need to agree on the terms of the settlement agreement, the preliminary hearing has been postponed until April 15, 2022,” RIA Novosti quoted the press service of the court as saying.

On July 30, the Arbitration Court of the Krasnoyarsk Territory registered a claim by the Federal Agency for Fishery against NTEC for 58.7 billion rubles.

The company is required to recover damage caused to aquatic biological resources in the amount of 58.7 billion rubles.

The agency claims that the fuel leak has damaged the entire water area of ​​the Norilo-Pyasinsky lake-river system.

The accident occurred on May 29, 2020 on the territory of CHPP-3 of the Norilsk-Taimyr Energy Company.

It is part of the Norilsk Nickel Group.