China News Service, September 8 According to the official Weibo news of the Propaganda Department of the Zhengzhou Municipal Party Committee, the "July 20" heavy rain disaster caused the entire Zhengzhou Metro network to be suspended. On September 8, the reporter learned from the Zhengzhou Metro Company that the Zhengzhou Metro will The passenger-carrying operation was resumed in two batches on September 12th and 15th.

  It is understood that, on September 12, the first phase of Line 1, Line 2 (from Liuzhuang Station to South Fourth Ring Station), and the suburban line will resume passenger operations; on September 15, the second phase of Line 2 (Jia Jia He station to Liuzhuang station), Line 3, Line 4, Line 5 will resume passenger operation; Line 14 Phase I due to equipment replacement, etc., temporarily does not have the conditions to resume operation.

  After the torrential rain disaster, Zhengzhou Metro established a work group for emergency repairs and production and operation recovery, and organized more than 3,000 professional and technical personnel from design units, participating units, system integrators, equipment suppliers, maintenance and maintenance units, and some domestic subway companies. Put into emergency repair work.

  As of August 19, the Zhengzhou Metro Line Network has achieved no-load operation except for the first phase of Line 14.

Since August 22, the transportation department has commissioned two safety operation evaluation units to organize experts to carry out a special safety evaluation for the resumption of operation of the Zhengzhou subway line network without load. By September 4, 6 lines (Line 1, Line 1, Line 2, Line 3, Line 4, Line 5, Suburban Line) special safety operation assessment, and issued an assessment report that "has the conditions for resuming operation".

Currently, the Zhengzhou Metro operating unit is carrying out re-testing, re-inspection and re-confirmation of various systems in accordance with operating standards, and will resume passenger-carrying operations on September 12 and 15.

  At the initial stage of resumption of operation, the operating hours of Line 1, Line 2, Line 3, Line 4 and Line 5 are from 6:00 to 23:00, and the peak driving interval of Line 1 and Line 2 is about 5 minutes, and the peak driving time is about 5 minutes. The interval is about 7 minutes; the peak driving interval of Line 3, 4, and 5 is about 6 minutes, the driving interval of Line 3 and Line 5 is about 8 minutes, and the driving interval of Line 4 is about 10 minutes; the suburban line operates The time is 6:00-22:00, the peak driving interval is about 10 minutes, and the flat peak driving interval is about 14 minutes.

  According to the news, according to the requirements of Zhengzhou Epidemic Prevention and Control Announcement No. 36, passengers must wear masks all the way into the station, check their health codes, and take the subway after the temperature is normal.

Zhengzhou Metro will continue to prevent and eliminate epidemics in public areas to create a good travel environment for passengers.

At the same time, citizens are reminded to queue up in an orderly manner and not to gather in the station.

Citizens can obtain subway operation updates through the official Weibo and WeChat public accounts of the "Zhengzhou Metro" and "China Construction Shenzhen Railway Line 3". If you need help, you can call the Zhengzhou Subway Service Hotline 55166166 or the Zhengzhou China Construction Shenzhen Railway Service Hotline 89820000.

  Zhengzhou Metro will closely monitor changes in passenger flow, organize standby trains to run on-line in due course, and make every effort to ensure the travel of citizens.