display

Tribsees (dpa / mv) - Once again, residents near Autobahn 20 at Tribsees have to expect a day full of noise.

The reason for this is the full closure of the Trebeltalbrücke in the area of ​​the construction site at the former motorway hole, as the Autobahn GmbH reported.

Work such as the removal of a construction pit or the concreting of a partial area of ​​the new floor slab would be pending.

Due to the limited space, this work could only be carried out from the available lane.

In addition, maintenance work is due on the temporary bridge.

The traffic will be diverted via the state roads 19 and 23, there are the villages of Langsdorf and Böhlendorf.

The A20 had sagged and collapsed near Tribsees in autumn 2017.

There was a huge gap.

Since December 2018, traffic has been slowly rolling over a temporary bridge.

The complete completion of the motorway is expected at the turn of 2023/24.

display

© dpa-infocom, dpa: 210413-99-188820 / 2