<Anchor> It



has been confirmed that the Ministry of Land, Infrastructure and Transport, which is responsible for the construction of a new airport in Busan's Gadeok Island, which is being pushed by the politicians, has virtually opposed the opinion.

A member of the ruling party, who was reviewing the Gadeokdo special bill, lamented that it would not do the same for river maintenance in the neighborhood, but this bill is scheduled to be discussed at the judiciary committee today (25th).



Reporter Baekwoon on the report.



<Reporter> This



is the feasibility report of Gadeokdo New Airport sent to the National Assembly by the Ministry of Land, Infrastructure and Transport.



It was analyzed that the risk of accidents increased, saying that the nearby Jinhae-gun airfield and the airspace for safe flight operations overlap and the control service overlap with Gimhae Airport.



He pointed out that there is a high possibility that the runway will sink as much as the sea is reclaimed.



In addition, considering the efficiency of transfer issues, and including military facilities for domestic and international flights, the project cost is estimated to reach 28.66 trillion won.



This is four times the estimated value of Busan City of KRW 7.5 trillion.



We have also attached the results of legal advice that civil servants knowing about procedural issues and refusing to object to them may constitute job abandonment.



The Blue House reduced its meaning as it was just an opinion given before, but the opinions of the ruling and opposition lawmakers who reviewed the bill last week asked, "Do you start with construction before the final design?" "Is the law come out?"



However, the special bill of Gadeok Island exceeded the threshold of the standing committee 40 days before the Busan Mayor's election.



The special law is expected to be presented at the plenary meeting tomorrow if it passes the judiciary committee today.