Tribsees (dpa / mv) - Before handing over responsibility for the major construction site on the A20 at Tribsees from the state to the federal government in the new year, Transport Minister Christian Ebene (SPD) was satisfied with the progress of construction.

254 of the total of 308 bored piles are currently in the ground, said level during a visit to the construction site on Wednesday: “We are handing over the construction site at a stage in which, in our opinion, all the prerequisites are in place so that the federal government can complete it quickly and efficiently . "

As part of the repair of the A20 near Tribsees, the northern carriageway west of the existing Trebel valley bridge towards Lübeck is currently being built.

According to level, the work is on schedule.

It can currently be expected that all structures in the direction of Lübeck will be finished by the end of 2021.

The major construction site on the most important east-west connection in Mecklenburg-Western Pomerania has existed since 2018 after the A20 at Tribsees sagged and collapsed.

There is still no definite clarity about the cause of the collapse.

Since December 2018, traffic has been rolling over a temporary bridge.