Hamburg (dpa / lno) - Three accidental damage on motorways around Hamburg should be removed by the weekend.

After the fire of a car on the B75 between the Wilhelmsburg and Kornweide junctions, the asphalt repair is planned for this Thursday.

The traffic to the south will be guided past the construction site in one lane between 9:00 a.m. and 2:00 p.m., the Autobahn branch north announced.

The interchangeable traffic system at the B5 crossing over the A1 in Billstedt is to be repaired on Friday morning.

The facility directs traffic over the new southern B5 bridge with one or two lanes as required.

The northern bridge is currently being renewed.

Motorists must follow a detour during the repair.

A noise protection wall on the A23 between Eidelstedt and Halstenbek-Krupunder is to be restored on Saturday and Sunday.

At the end of September, a 60-ton crane went off the road and hit the noise barrier.

During the construction work between 6.30 a.m. and 5 p.m. there is only one lane available to drivers in the direction of Heide.