This was reported by the State Production Association "Belenergo".

“On October 3, a program was successfully implemented to put into operation an overhead high-voltage transmission line 330 kV“ Belarusian NPP - Ross ”(VL-330).

This line with a length of 250 km connected the high-voltage switchgear of the BelNPP with the 330 kV Ross substation, further ensuring the transfer of energy from the Belarusian NPP to the western part of the republic's energy system, ”the statement says. 

It is noted that this is the last of the seven high-voltage transmission lines connecting the nuclear power plant with the country's energy system.

Earlier it was reported that the launch of the Belarusian nuclear power plant (BelNPP) is scheduled for November 7.