Construction was halted in early October after the County Administrative Board discovered numerous deficiencies during an environmental review on the record.

Since then, the work has been stalled and the company has worked to fix the problems in the area. Above all, there are quantities of excavation dumps dumped in the wrong places.

The County Administrative Board then wrote that the company did not appear to have control over its operations.

Acceptable accounting

After the meeting today, Anna Bäckman, environmental manager at the County Administrative Board, says that the company has reported the measures it has taken to bring order and that it feels ready to resume work on site.

- We have received an acceptable report from the company, says Bäckman.

As soon as possible

When the job can get started is still a bit unclear, but according to Per Nordlund CEO Nysäter Wind, this should be done as soon as possible.

"That's because our subcontractor Nordex can get started," says Nordlund.