IVO's press service states that SVT has started a case based on the media reporting on lack of material.

The inspection therefore requires answers to the following from the five regions involved.

  • A risk and impact assessment was carried out prior to the change of distributor and if it has been done, what did it show and were any measures taken?
  • What patient safety risks have been identified due to the lack of materials and what measures have been taken?
  • How has priority been given to care and treatment?
  • How will you investigate and follow up on the effects of what happened to avoid similar situations?

The text is updated.