• The Fire Brigade at work on the site of the collapse of the viaduct in the A14
  • Overpass collapsed in A14, the video shot from a police helicopter
  • Viaduct collapsed in Ancona, the video of the Fire Department
  • Crolla flyover on the A14, two dead and two wounded. The arrival of aid
  • Overpass over A14: two dead. Eliambulanze to collect the injured (Video)
  • Ancona, an overpass collapses on the A14, at least two dead. The photos

Share

10 March 2017

Autostrade per l'Italia "urged the companies that designed and executed the works on the collapsed flyover in A14 a very detailed report on what happened, to ascertain any human errors and evaluate possible actions to protect them". The construction site, says a note from the company, "had been started on February 7th and it should have been concluded, as far as activities on the batteries aimed at raising the flyover were concerned, on March 31st".

In the hours immediately following the collapse, Autostrade had spoken of "a tragic unforeseeable accident, caused by the collapse of temporary batteries on work to raise the overpass necessary to restore the height of the work to the new level of the highway plan, after the widening of the three-lane motorway. This is not therefore a question of structural failure ". Yesterday morning, Autostrade always announced that the activities on the bridge "had been completed at 11:30 am and, at the time of the accident, the staff was carrying out ancillary activities".

The minister Delrio already signed the decree of appointment of the inspectorate commission of experts of the department to verify and analyze what happened. The company responsible for the works, Delabech, carried out similar works on 19 other overpasses of the same section.

The person in charge of the works: down the temporary supports
"The structure of the bridge's temporary supports went into crisis". Thus the engineer Giovanni Scotto Lavina, head of the procedure at Autostrade per l'Italia, on the sidelines of an inspection along the A14. "We are making the necessary investigations - he repeats -: the bridge went into crisis due to the reasons we will have to ascertain. The temporary support structure has remained intact, we would like to say this. It is a concrete structure: the concrete structure that supported the beams did not go into crisis until the start of the overpass lifting operations. The structure of the set of provisional supports went into crisis ''.

On the spot, hard work was carried out last night to clear the blocked roadway. The technicians on site have "dissected" the collapsed bridge and transferred the materials out of the highway axis. And as far as we learn from traffic police sources, both highway tracks have been reopened.

Human error and structural failure?
It will be the investigation opened by the prosecutor's office of Ancona to establish the cause of the collapse of the overpass occurred at 13 yesterday in Camerano (Ancona), between the exits of Loreto and Ancona South, while three workers of the Delabech company were raising the span of the bridge with of the jacks. Meanwhile, the death of a couple is being mourned: Emidio Diomede, 60, and Antonella Viviani, 54, of Spinetoli (Ascoli Piceno) were traveling at that time aboard a Nissan Qashqai. They crashed violently against the rubble. The workers, however, were not seriously injured after falling from a height of 6-7 meters: "We didn't understand anything, at one point everything collapsed, and we found ourselves on the ground" said one of them to rescuers. He is a 47-year-old resident of Frascati, who suffered a broken wrist; a 57-year-old who lives in Montecompatri, who suffered a head injury of medium severity and multiple bruises. The third person was treated for minor bruising. They are all of Romanian origin.

Witness: I feel miraculous
Anna Maria Mancinelli of Porto Sant'Elpidio (Fermo) feels "miraculously" traveling on the A14 motorway on a car that stopped "a hundred meters before the collapsed bridge. First we saw some cars stopped, then a crushed vehicle and we understood what had happened. I am a laywoman, but we were returning from a press conference to present the Pro Loco festival in Ancona on March 12th in Loreto, where the UNPLI banners will be blessed. is the fact that we are in the territory of Loreto make me feel like a miracle ".

The mayor of Castelfidardo: "Something went wrong"
"The workers were raising the span of the bridge with jacks, when the structure gave way: obviously something went wrong," said the mayor of Castelfidardo (Ancona), in whose territory the accident occurred, Roberto Ascani, for the which "it is inconceivable to perform works of this nature without closing the A14". "The relief efforts were immediate," the prefect of Ancona, Antonio D'Acunto, made a point of urgently summoning an operational committee on the road system, which went completely haywire. But the controversy, of course, is not lacking, also considering the previous ones. The last one, the bridge that collapsed last October 28th in the municipality of Annone Brianza, where the overpass that overlooks the lanes of the busy Superstrada 36 Milan-Lecco was sold, causing one dead and four wounded.

"Italy falls to pieces"
"It is a shame unworthy of a civilized country. Instead of going around promising and chatting, Renzi and Gentiloni report back to the House and do something concrete to prevent deaths and injuries", the League secretary Matteo Salvini attacked. "Italy falls to pieces", comments by Roberto Calderoli, vice president of the Senate. "What happened today is unacceptable - the words of the Transport Councilor of the Marche, Anna Casini -. We hope that the judiciary will ascertain all responsibilities as soon as possible". "Faced with the serious tragedy, it is advisable to clarify things as quickly as possible," said deputy Pd Michele Anzaldi, a member of the Chamber's Transport commission. "I asked the leaders of Autostrade per l'Italia to explain to the Senate Public Works Commission the causes of the tragic collapse of the A14 overpass. The hearing I have already arranged will take place very quickly. I hope that Minister Delrio will also in the Commission as soon as he is in possession of every element of knowledge on the incident ", announced the president of the Commission Altero Matteoli. The workplace accident commission is instead evaluating the opening of an investigation dossier, said the president, the Senator from Marche, Pd Camilla Fabbri.

Power of attorney: there were more companies and several workers at work
In the construction site of the collapsed bridge on the A14 at least two companies worked, "but there are also others that we are trying to identify". This was said by Ancona prosecutor Elisabetta Melotti and the prosecutor of the Irene Bilotta investigation. In addition to Delabech srl of Rome, which was working as a subcontractor on behalf of Pavimental, a subsidiary of Autostrade, there was also the Nori Group of Castelnuovo di Porto (Rome). There are also several workers at work, at least two teams.