[Explanation] On November 25, the reconstruction and expansion project of the Nansha-Zhuhai section of the Guangzhou (State) Macau (Men) Expressway was held in Zhongshan City, Guangdong Province. It is expected that the reconstruction and expansion of the entire line will be completed by the end of 2027.

  [Explanation] The Nansha-Zhuhai section of the Guang'ao Expressway was completed and opened to traffic in December 1999. It is the first expressway directly leading to the Macau region from the inland.

Today, as an important part of the "A"-shaped development axis of the core area of ​​the Guangdong-Hong Kong-Macao Greater Bay Area, with the rapid growth of traffic volume, improving the traffic service capacity of this expressway has become an urgent livelihood issue.

  [Explanation] It is understood that the reconstruction and expansion project of the Nansha-Zhuhai section of the Guang'ao Expressway starts at the Tanwei Junction Interchange in Huangge Town, Nansha District, Guangzhou, and ends at the Zhuhai Toll Station, Nanlang Street, Cuiheng New District, Zhongshan City, with a mileage of about 50.43 kilometers.

The project expands the above road section to two-way eight-lane or two-way ten-lane.

The reconstruction and expansion of the project is faced with many problems: the road construction time is relatively early, the traffic volume is large, the requirements for smooth flow and safety are high, and the pipelines along the road are densely distributed.

The relevant person in charge of the construction unit stated that he will take multiple measures such as "smart road network management and control" to ensure the construction progress and quality.

  [Same period] Mou Jun, executive deputy manager of the TJ1 contract section of the reconstruction and expansion project of the Nansha-Zhuhai section of the Guang'ao Expressway

  Because you can see that the traffic flow on our site is very large, so when we are carrying out reconstruction and expansion, the traffic flow is very large, and how to carry out a traffic conversion is very important.

Through the cooperation of all parties, a relatively complete traffic treatment plan was compiled, and then implemented in stages after review. This is the first one.

The second is the reconstruction and expansion project of the old bridge, which is to use our experience in reconstruction and expansion projects in the Pearl River Delta region for so many years, and then compile some mature construction plans, and then send technical forces to complete it.

  [Explanation] According to reports, after the reconstruction and expansion project is completed and opened to traffic, the transportation links between Nansha, Zhongshan, and Zhuhai in Guangzhou will be strengthened, and the interconnection of the Guangdong-Hong Kong-Macao Greater Bay Area will be accelerated. Circle" is of great significance.

  [Concurrent] Liu Zhi, Deputy Director of the Reconstruction and Expansion Management Office of the Guangzhou-Zhuhai Section of the Beijing-Zhuhai Expressway

  The main purpose is to solve the pressure of the current north-south longitudinal traffic flow on the west bank of the Pearl River Estuary in the "A"-shaped channel of the Guangdong-Hong Kong-Macao Greater Bay Area, and to bring convenient traffic conditions to the development of the Guangdong-Hong Kong-Macao Greater Bay Area.

  (Reported by reporter He Junjie and Cai Minjie from Zhongshan)