(Fighting New Coronary Pneumonia) Three days in advance!

Nearly 3,000 beds have been put into use at the emergency transfer point in Baiyun District, Guangzhou

  Chinanews.com, Guangzhou, November 20 (Guo Jun, Wu Qiong, Chen Shushan) On November 20, nearly 3,000 beds at the emergency transfer point in Baiyun District, Guangzhou were officially opened, and the first batch of quarantined personnel was ushered in that night.

  "The project was delivered in two batches. After the first batch of delivery was completed on the 18th, the medical staff moved in immediately. The second batch of delivery was originally planned to be on the 23rd. At present, China Construction Fourth Engineering Bureau, as the project leader, took the lead in completing the construction task and fully delivered it three days in advance. "Wu Erlong, on-site commander of the emergency transfer point project in Baiyun District, China Construction Fourth Engineering Bureau, told reporters that the construction scope of China Construction Fourth Engineering Bureau covers an area of ​​about 49,100 square meters, with a total construction area of ​​about 18,900 square meters, providing a total of 1,746 beds. The content includes old apartment building renovation, K-board warehouse renovation warehouse, packing boxes in the new site area and supporting systems such as water and electricity, fire protection, sewage discharge, and ventilation.

  The project construction team entered the site urgently after receiving the task on November 9, and quickly assembled a construction team of more than a thousand people and more than a hundred large machines.

In view of the short construction period of the project, the complex situation on the site, and the need to carry out design and construction during the construction process, the construction team worked in multiple ways and worked in 24-hour shifts.

"We completed the overall design task of the project in three days, and completed packing boxes, K-board houses and other materials into the site within two days, providing sufficient guarantee for construction operations." said Wang Shubing, the project leader of the Guangzhou Branch of the First Company of China Construction Fourth Engineering Bureau.

  Wu Jiquan, project leader of the South China Construction Company of China Construction Fourth Engineering Bureau, said that the old and renovated apartment building that was the first to welcome medical staff was abandoned, with piles of garbage and no water and electricity. Without waiting or relying, we will take the lead in realizing the "three links" of water, electricity and roads.

At the same time, in the face of many difficulties such as simultaneous design and construction in the early stage of construction, the project team planned in advance, made bold decisions, actively coordinated, continuously optimized the process arrangement, made full use of interspersed construction, and set up a "elimination item list" to check item by item to ensure the project The safety, quality, and progress of the entire construction process are stable and controllable, laying a solid foundation for on-time delivery.

  According to Zhang Cong, the project leader of the China Construction Fourth Engineering Bureau Installation Company, the construction party, the construction progress plan was prepared reasonably for the project, and the grid management model was adopted to ensure smooth construction in each area. Temporary buildings take one month, and now it only takes ten days to fully deliver.

  The emergency transfer point project in Baiyun District, Guangzhou City is located in the Shatai Cargo Yard on the northwest side of Huangzhuang South Road, Baiyun District, Guangzhou City. The total area of ​​the project is about 152,000 square meters, and the construction area is 83,000 square meters. After completion, it will provide about 6,342 beds for transfer personnel, including 5,567 emergency beds and 775 medical beds, which can accommodate nearly 12,700 people for isolation.

(Finish)