JERA's Anegasaki Thermal Power Station Unit 5, a thermal power generation company invested by TEPCO and supplying power to the TEPCO jurisdiction, was preparing to resume operation from the morning of the 30th, but there was a problem with the equipment. , The restart was delayed before 11:00 am.

Since the thermal power plant needs to gradually increase its output from the start of operation, it is planned to operate at about half of the maximum output of 600,000 kW during the evening of the 30th, when the power supply and demand is the most severe.

Anegasaki Thermal Power Station Unit 5 has been in operation for 45 years since it started operation, and has been shut down since March due to its deterioration. Was scheduled to resume operation on July 1, but one day ahead of schedule.