The tourist facility, which is under construction on the premises of the Toyosu Market in Tokyo with the aim of opening again next year, may be delayed from the original schedule due to the influence of the new coronavirus, etc., and there is a possibility that it will be three years later. We are requesting the operator of the facility to shorten the construction period.

At Toyosu Market, the largest wholesale market in Japan in Koto Ward, Tokyo, the construction of a tourist facility, "Senkaku Manrai Facility," is underway to create a lively atmosphere on the premises.



The facility was agreed to be completed in December next year between the Manyo Club, which is in charge of operation, and the capital, and was scheduled to open again next spring.



However, according to the capital, there was a notification from "Manyo Club" that the completion would be delayed by about 10 months.



According to "Manyo Club", the cost increased due to the increase in construction demand before the Tokyo Olympics and Paralympics, and a part of the design was revised. The reason is that it took.

If the completion is delayed, the opening will be delayed, and the spring of next year may be three years later, the opening of the new year in 2024.



"Manyo Club" told the interview that "we are discussing with the construction company so that the completion time can be accelerated."



On the other hand, the capital has asked the details of the "Manyo Club" and is requesting a shortening of the construction period.