On May 30, the first water purification plant project in Xiong’an New District, the first water purification plant project in Xiong’an New District, started by China Construction Installation Group Co., Ltd., has entered the stage of decoration finishing and equipment commissioning.

The project is expected to be put into operation at the end of June, with a daily production of 150,000 tons of purified water, which can ensure that 170,000 residents in Rongdong area can use high-quality drinking water.

The picture shows the aerial photography of the construction site of the No. 1 water supply plant in the starting area of ​​Xiongan New District.

(Photo by drone) Photo by China News Agency reporter Han Bing


Release time: 2021-05-30 20:50:16 【Editor: Tian Bochuan】