China News Service Nanchang, July 10 (Xu Yinghua, Dai Yi reporter Liu Zhankun) On the evening of July 9, Xinpeixu, located in Datangping Township, a newly built district in Nanchang City, Jiangxi Province, was successfully sealed.

On July 9th, due to heavy rainfall, a dangerous situation broke out in Xinpeixu dike, Datangping Township, Nanchang New District. Photo by Xu Yinghua

  Over the past few days, Jiangxi Province has experienced continuous regional rainstorm weather, during which the average rainfall in the province reached 149 millimeters. Affected by heavy rainfall, the Xinpeixi dike in Datangping Township, Nanchang City, broke out at 8:00 on July 9th, with a rupture of about 14 meters, a flow rate of about 5 meters per second, and a difference of 2 meters between the upper and lower reaches. Downstream is a 7,200 mu farmland protection area, the situation is grim.

On the 9th, a cripple danger occurred in Xinpeixu dike, Datangping Township, Nanchang New District. The on-site velocity was about 5 meters per second, and the difference between the upper and lower reaches was about 2 meters. The downstream of the breach was 7,200 acres of farmland protection area. The situation was grim. Photo by Zhang Wanlong

  As a national emergency rescue professional, after receiving the task request from the Nanchang City Anti-Finger and Emergency Management Bureau, the Nanchang Branch of China Anneng Second Engineering Bureau immediately dispatched a professional team to the front line, with a total of 67 people and 7 sets of equipment. Resolutely start a tough battle against floods and rescue.

At the scene, the rescue team decided to adopt a double-headed occupation scheme (block stone foot protection, reinforced cage occupation, small stone filter, clay anti-seepage), the break length is 15 meters. Photo by Zhang Wanlong

  At the scene, the rescue team set up a commanding post to break forward, clarify the command formation, and actively discuss the plan with the relevant departments of the local government, and decided to adopt the double-headed occupation plan (block stone foot protection, steel cage occupation, small stone filter, clay anti-seepage) , The break length is 15 meters.

At 8 p.m. on July 9th, Xinpei Weikou successfully closed the dragon, realized the restoration of the embankment, and basically completed the handling of the dangerous situation. Photo by Zhang Wanlong

  At 7 o'clock on the 9th, the on-site flow rate increased from 5 meters per second to 7 to 8 meters per second. The rescue and disaster relief team members wore raincoats and performed their duties in the busy site, pulling an orderly and efficient line on the dam. Working line. After continuous emergency repairs, 3 kilometers of emergency roads were built, 1,000 square meters of paved stones were used, 300 vehicles were fed bilaterally, and 3500 square meters were filled. At 8 pm on the 9th, Xinpeixu successfully closed the dragon, realized the restoration of the embankment, and basically completed the handling of the dangerous situation.

  According to the Nanchang Branch of China Anneng Second Engineering Bureau, at present, the danger of the Xinpeixu dike break in Datangping Township has been effectively controlled and no casualties have occurred. According to the weather forecast, in the next three days there will be a new round of rainfall in northern Jiangxi. The rescue team will seize the favorable opportunity to formulate a repair plan, widen and thicken the dam body as soon as possible, and complete the repair work. (Finish)