Why has a 100 square meter house not been completed after 450 days of installation?

  On June 9th, Chengdu citizen Mr. Li went to his new house again to check, but what came into sight was not the repair of a new home, but the messy "semi-finished products".
  At this time, more than 450 days have passed since he signed a contract with Sichuan Longfa Building Decoration Engineering Co., Ltd. (hereinafter referred to as "Longfa Company") to start the renovation.
  Mr. Li said that from the start of construction in March 2019, to the "designer drunk driving being suspended for work" in July 2019, and then to the completion of the "failure of Longfa supervision due to inadequate supervision due to inadequate supervision" in May 2020, the decoration has exhausted the whole family.
  Faced with doubts, Mr. Zeng, the general manager of Longfa Company's Chengdu West District, responded that the delay in the decoration period was caused by the epidemic situation and the owner's request for rework. Regarding the damage to the floor heating installed by Mr. Li, the company does have "unsuccessful supervision" and is willing to bear part of the loss.
  "Full of 450 days, except for 90 days after the epidemic was suspended, there are still 360 days left. A whole 100-square-meter house can't be installed all year long?" Mr. Li did not agree with the attitude of Longfa Company.

Tucao
designer perfunctory mistakes the apartment

  Mr. Li’s new house is located at Ronghua North Road, Chengdu, with a property area of ​​102 square meters. “This is a house bought for the children to study in the future. The old house has been sold and the new house has not been installed. I am renting a house now.” He says.
  Mr. Li introduced that as early as March 2019, he signed a decoration contract with Longfa Company and started construction on March 11. However, the designer was too perfunctory and the design he made had mistaken the apartment type, Zhang Guanli Dai.
  On April 20, 2019, Mr. Li and Longfa Company re-signed the "Decoration Contract", stipulating that Longfa Company contracted labor and some auxiliary materials. The main materials were purchased by the owner themselves, and the total decoration amount was more than 120,000 yuan.
  By July 2019, Mr. Li suddenly found that he could not contact the designer. "I only learned after asking that the designer's drunk driving was detained by the police and the decoration was also suspended. I applied to Longfa to change the designer, but I ignored him. "
  Mr. Li said that in August 2019, the designer finally came out and the decoration started again, but until the Spring Festival, a full five months, although Longfa has been saying that the decoration, but the progress is very slow, the holiday is closed again before the Spring Festival .
  In the Spring Festival of 2020, the epidemic situation hit, until April 3, the decoration did not resume work again.

Questioned that the
floor heating was smashed and the decoration company tried to deceive the owner

  After many twists and turns, I thought this was the end, but on May 20, the decoration went wrong again.
  Mr. Li said that the husband and wife were too busy to work, so they entrusted Longfa Company to coordinate the construction. "According to the contract, Longfa will have a foreman to supervise the scene, but he rarely comes to the scene and entrusts his son to the scene, and this young man is not qualified or responsible."
  Mr. Li said that on the 20th, the installation of floor tiles team approach, "the construction team encountered problems, he asked the foreman how to deal with, foreman let workers hit hard, the results have been paved to warm the pipes smashed, missed a ground water."
  Also helping Lee Angrily, after the floor heating pipe was smashed, the foreman didn't notify himself, privately instructed the worker to change a pipe, and the worker did not dare to take the initiative to inform Mr. Li, he only knew this.
  "In such a big company, it is really irresponsible to do so." Mr. Li said.

Respond to the
company's lack of supervision and willing to bear part of the loss

  A house of more than 100 square meters has not been completed after more than a year of renovation. Why? The floor heating pipe is smashed, should the decoration company bear the responsibility? On the 9th, Mr. Zeng, General Manager of Chengdu West District of Longfa Company responded.
  Mr. Zeng said that Mr. Li’s house had not been completed for more than a year since it was completed because of various reasons. The first was the impact of the epidemic, and the second was the owner’s repeated requests for rework. As for "the designer's drunk driving was arrested, which resulted in a delay of more than one month", he said "this is a personal problem and has nothing to do with the decoration."
  After the floor heating pipe was smashed, Mr. Li consulted and learned that because the pipe was a closed loop and had been tested, there was a damage. If only one section was replaced, water leakage and pipe explosion may occur in the future. If you want to eliminate hidden dangers, you must replace the entire circuit, the cost is about 8,000 yuan. To re-lay the pipeline, it is necessary to pry open the paved floor tiles, which will cost tens of thousands of yuan.
  In this regard, Mr. Zeng responded that the company did not have adequate supervision and was willing to bear part of the loss. Mr. Li can buy floor heating pipes and ceramic tiles by himself, and Longfa arranges workers to lay the shop. "The owner put all the responsibility on our decoration company. , This is not acceptable."
  At present, Mr. Li has complained to the government department and has hired a lawyer to prepare to protect his rights through legal channels.