Work on Cable 1, the first urban cable car in Ile-de-France, has begun in Créteil (Val-de-Marne).

The machines are installed along the departmental road 1, near the future Pointe du Lac du Cable 1 station of metro line 8, reports Thursday

Le Parisien

.

It is a question of carrying out "the removal of the central reservation of the D1 road and the diversion of the electricity and sanitation networks" specifies Ile-de-France Mobilité (IDFM) which will be responsible for operating the future cable car. .

The work will take place until the summer of 2023, Monday to Friday from 8 a.m. to 5 p.m.

Traffic could be disrupted.

One lane is neutralized and the speed is limited in the sector to 30 km/h.

Up to eleven thousand travelers every day in 2025?

The infrastructure works will begin next year with the construction of the stations, the lifting of the pylons and the pulling of the cable.

This phase will continue until the summer of 2024.

The cable car, which will connect Villeneuve-Saint-Georges and Créteil via Valenton, will have five stations.

It will transport 11,000 passengers per day and up to 1,600 per hour.

Its commissioning is expected in 2025.


World

The longest cable car in the world soon to be built on the island of Dominica

Planet

Lyon: After the abandonment of the cable car project, what alternatives to serve the west of Lyon?


  • Creteil

  • Ile-de-France

  • Paris

  • Works

  • Cable car

  • Transportation