<Anchor> The



reconstruction work of Dunchon Jugong Apartment in Seoul, which will accommodate more than 12,000 households, has been halted for a week.

The reconstruction association and the construction company were arguing over the additional cost of construction, but there was another hidden reason.



Reporter Han Sang-woo reported.



<Reporter> The



suspension of Dunchon Jugong construction has been known as a conflict over construction costs.



But the situation underneath was different.



This is an official letter sent by the Reconstruction Association to the construction company right before the construction was stopped.



Although there was a proviso that there was an ex post verification, I wrote that the construction cost would be raised as the construction company had requested in the meantime.



The money problem is practically solved.



However, another condition was attached.



The union presented 19 items and specific companies such as kitchen and bathroom furniture and tiles, saying that it would upgrade the finishing materials.



He even offered to pay more if there was an extra cost.



However, the construction company countered that it was difficult, saying that it had already placed an order for finishing materials according to the existing contract.



[Construction company official: I have never seen such a change in finishing materials in the middle of construction.

It can be seen that such cases are rare in reconstruction and redevelopment sites...

.]



Some members complained that the union didn't talk in advance.



[Dunchon Jugong Reconstruction Association Member: If you want to upgrade it, you will definitely have to pay extra for it.

You need to inform them about it and get consent.

The union leadership is unilaterally making demands from the contractor.] The



union said it was a 'mistake' to ask for a specific company's product, but said, "The union has the right to use a good product."



[Kang Jeong-won/Dunchon Jugong Reconstruction Association Advisory Committee: To argue that something that was decided 4-5 years ago has no choice but to apply now, is actually something we are suspicious of.]



Mutual trust is weak due to endless conflict As the country's largest reconstruction project continues to decline, there is a possibility that it will be idle for a while.



(Video editing: Nam Il, VJ: Jung Young-sam)