Xinhua News Agency, Jinan, April 17 (Reporters Chen Hao and Shao Luwen) Under the warm spring sun, the construction site of the North Yellow Tunnel Project on Jiluo Road in Jinan City was busy.

Crawler cranes, excavators, forklifts and other construction machinery roared, and workers were pouring concrete for the foundation pit cushion of the shield machine's starting shaft to prepare for the shield starting operation.

  At the entrance of the construction site, several employees of the construction unit China Railway 14th Bureau Group are measuring the temperature of those entering the site.

"In the last month, we have done 10 rounds of nucleic acid testing for all employees on site." He Xiaobin, secretary of the project party branch, said that the North Extension Tunnel of Jiluo Road passing through the Yellow River is an important link between Jinan's new and old kinetic energy conversion starting area and the main urban complex traffic corridor. project.

In order to ensure the progress of the project on schedule, the project department maintains the "hard core protection" and does not relax. The real-name system for personnel enters the site, and foreign materials must be transported to the transition area for disinfection to ensure that the epidemic prevention and control does not leave dead ends.

  Transportation is the lifeblood of the economy.

At present, some key projects in the fields of highways, railways, airports, ports and shipping, and rail transit in Shandong Province are under construction. The competent authorities and construction units are focusing on epidemic prevention and control on the one hand, and project progress on the other, so as to grasp the "golden construction period" in spring and run Out of the project construction "acceleration".

  On the 14th, at the site of the Jinan-Weifang Expressway project invested and constructed by Shandong Expressway Group, the box girder pouring operation of the Beizhentou Bridge is in progress.

  Xie Guomu, director of the Jiwei Expressway Project Office of Shandong Expressway Group, introduced that this is the first new smart expressway project in Shandong, which is of great significance to promoting the interconnection between the Shandong provincial capital economic circle and the Jiaodong economic circle.

The project department has solidly implemented the responsibility for epidemic prevention and control, established a prevention and control ledger covering all participants, and implemented a daily reporting system for epidemic prevention and control. The participants made every effort to speed up the construction progress. This year, an investment of 4.01 billion yuan has been completed, which is the original plan of the project. 136.5%.

  The 170-kilometer-long Ji-Zheng High-speed Railway Shandong section is an important part of Shandong's "four horizontal and six vertical" comprehensive transportation corridors. After the opening to traffic, the shortest travel time from Jinan to Zhengzhou will be shortened from the current 3.5 hours to 1.5 hours.

"The construction of some key nodes is difficult, the operation time is short, and the safety risk is high. We have organized experts to conduct several demonstrations and optimizations on the construction plan, overcome the impact of the epidemic, and reasonably deploy large-scale machinery and ensure the supply of materials. The project is progressing smoothly." China Railway Tenth Bureau Qin Chuanjun, the project manager of the Zhengji First Branch of the Qingdao Company, said.

  The reporter learned from the Shandong Provincial Department of Transportation that many high-speed rail lines in Shandong Province are under intense construction.

This year, Shandong will speed up the construction of 5 projects under construction, including the Shandong section of the Jizheng high-speed railway, the Weiyan high-speed railway, and the Lai-Rong high-speed railway, and start the construction of the Tianjin-Weifang section of the Beijing-Shanghai high-speed railway auxiliary channel, the Xiongshang high-speed railway, and the Jibin high-speed railway. The two projects of the Huangtai Link Line and the Jilai High-speed Railway will exceed 2,400 kilometers by the end of the year.

  The construction of ground transportation is relentless day and night, and projects such as port airlines and airports are also in full swing.

  The Xiaoqing River resumption project with a total investment of about 13.6 billion yuan is planned to be completed by the end of this year. After completion, Jinan will become a city connected to the sea. The construction progress of each construction node is steadily advancing, and the completion progress of some indicators exceeds 90%; Yantai The construction of the second phase of the airport project and the relocation of Jining Airport is also in full swing.

  "What stage is the project construction at now?" "Have you encountered any difficulties?" "Can it be completed on time?" Similar questions frequently appear in the construction of transportation projects in Shandong Province.

  Guo Zhiyun, director of the comprehensive planning department of the Shandong Provincial Department of Transportation, introduced that Shandong has established a leading group for the promotion of key transportation construction projects to strengthen communication and coordination with the local government and provincial departments, and regularly schedule the progress of the project.

In view of the difficulties and blockages encountered by the project, timely coordinate and dispatch all parties to solve them.

At the same time, starting from the whole process and all elements of land use and other procedures, parallel operations and stubble development are carried out to optimize the handling process.

  Guo Zhiyun said that on the basis of the "good start" for the construction of key Shandong transportation projects in the first quarter of this year, the Shandong transportation department will further refine the roadmap and clarify the start timetable to ensure that "more than half of the time and more than half of the tasks" in the second quarter. Make the construction of major transportation projects an important engine to promote the high-quality development of Shandong's economy.