China News Service, Xinjiang Shache, September 21 (Reporter Yan Wenlu) Xinjiang Shache-Hetian II 750 kV transmission line project N1001-N1002 site carried out on the 20th, the second line of the 220 kV car Tashi line was carried out for the connection of the line project The 750 kV Shache Substation will make the final sprint.

The total length of the 750 kV transmission line project from Shache to Hotan II is more than 320 kilometers, and the newly-built 682 base of the iron tower.

Photo by Huang Junhui

  The Shache-Hetian II 750 kV power transmission and transformation project is to promote the rapid economic development, social harmony and stability of the Hotan area of ​​Xinjiang, strengthen the connection between the Hetian power grid and the Xinjiang main grid, implement the "coal-to-electricity" project implementation, and improve the reliability of the power supply of the Hetian power grid. The key livelihood projects of power supply quality.

The project started in Qareke Town, Shache County, where the 750kV Shache Substation has been built, and ended in Langru Township, Hotan County, where the 750kV Hetian Substation has been built. Construction started on May 26, 2020. The total length of the line is more than 320 thousand. M, 682 foundation of the newly built iron tower.

The Shache-Hotian II 750 kV transmission and transformation project is one of the key livelihood projects in Xinjiang.

Photo by Huang Junhui

  It is reported that the foundation and towers of the 750 kV transmission line project in Shache-Hotian II have been completed. At present, only a total of nearly 1 km of lines at the terminal towers on both sides have not been erected.

In order to effectively reduce construction safety risks, the State Grid Xinjiang Construction Branch made fine arrangements to make full use of the power outage maintenance window to carry out the erection work at the remaining terminal towers.

  "The risk of live crossing is high and the potential safety hazard is high. In order to ensure the safe and high-quality completion of the construction tasks, we actively coordinated with the territorial company before the crossing, and adopted the whole process of power outage." State Grid Xinjiang Construction Branch Shache-Hotan 2nd 750 thousand Said Ma Zhonglong, project manager of the owner of the volt transmission line project.

  According to reports, the line erection work at the terminal towers on both sides of the Shah Station and Hotan Station is expected to be completed on September 25. In the next step, the State Grid Xinjiang Construction Branch will carry out the terminal tower section acceptance and elimination, line parameter testing, etc. Ensure that the project successfully completes the "zero defect" goal of commissioning.